The works will be completed under three phases, as detailed below.
Phase 1
Otterham Quay Lane, Upchurch will be closed from Monday 9th August 2021, with estimated completion by 22nd August 2021.
The road will be closed between the junctions with Lower Rainham Road and Horsham Lane, to the extent indicated by signs and barriers on site.
The alternative route is via Horsham Lane, Oak Lane, London Road, Otterham Quay Lane and vice versa.
Phase 2
Otterham Quay Lane, Horsham Lane & Wallbridge, Upchurch will be closed from Monday 16th August 2021, with estimated completion by 29th August 2021.
The roads will be closed between the junctions with Gibbs Lane and Horsham Lane, to the extent indicated by signs and barriers on site.
The alternative route is via Horsham Lane, Oak Lane, London Road, Otterham Quay Lane and vice versa.
Phase 3
Wallbridge Lane, Upchurch will be closed from Monday 23rd August 2021, with estimated completion by 27th September 2021.
The road will be closed between the junctions with Otterham Quay Lane and Oak Lane, to the extent indicated by signs and barriers on site.
The alternative route is via Oak Lane, London Road, Otterham Quay Lane and vice versa.
The closures are required for the safety of the public and workforce while gas main replacement works are undertaken by SGN.
For information regarding these closures please contact SGN on: 0800 111999, who will be able to assist with the scope of these works.