We are writing to let you know about our project to upgrade our gas network around The Poles area of Upchurch.
We are replacing our old metal gas mains and services with new plastic pipe. This essential work will ensure your community continues to receive a safe and reliable gas supply.
In consultation with Kent County Council, our contractor, WCB Utilities, who will be completing this project on our behalf, will start work on Monday 21st March for approximately four weeks.
To safely access our gas network, it will be necessary to close the following roads.
The Street
We will need to close The Street from outside property number nine to the junction with The Poles from 21st March for approximately four weeks.
The Poles
Our engineers will need to close The Poles from 23rd March for approximately three weeks.
Forge Lane
We will need to close Forge Lane from the junction with The Street to outside number twenty-three Forge Lane from 2nd April for two weeks.
Church Farm Road
Church Farm Road will need to be closed at the junction with Forge Lane from 2nd April for approximately two weeks.
Access will be maintained for residents and signed diversions will be in place.
We understand that people can get frustrated by roadworks, however we would not close a road unless it is unsafe not to.
We’re writing to residents and other local stakeholders to make them aware of our project and explain the details of our work. Please feel free to also share this information with anyone you think may be impacted by our project.
Yours sincerely
Sharon Dorrington
Stakeholder and Community ManagerSGN Gas